Secondary School Complex
Welcome to the Secondary School Complex Building Project webpage. This site serves as a central resource for information related to the District’s ongoing evaluation of facility needs and potential future building options. Our goal is to provide clear, accessible updates and materials so that community members can stay informed throughout the process. Please use the resources below to learn more about the studies, presentations, and discussions that have taken place to date.
Project Updates
October 28, 2025
Board Accepts RLPS Feasibility Study
The Elizabethtown Area School District Board of School Directors voted to accept the comprehensive feasibility study prepared by RLPS Architects.
- EASD Feasibility Study (prepared by RLPS)
October 14, 2025
RLPS Delivers Final Feasibility Study Presentation
Representatives from RLPS delivered their final feasibility study presentation, providing an in-depth review of facility needs, modernization options, and long-term recommendations for the district.
September 16, 2025
Public Information Session and Q&A Hosted by RLPS
Informational Session w/ Q&A Hosted by RLPS – Tuesday, September 16, from 6–8 PM, including an opportunity for public comment specifically regarding the secondary school complex project. Please note: a previous handout incorrectly listed the date as September 19; the correct date is September 16.
September 9, 2025
Board Receives Feasibility Study Progress Update
During the regularly scheduled board meeting on September 9, 2025, the Elizabethtown Area School District Board of School Directors received an update from RLPS Architects on the status of the feasibility study.
August 19, 2025
Community Tours Highlight Key Facility Challenges
The Elizabethtown Area School District invited community members to participate in guided tours of the middle and high school buildings on Tuesday, August 19, 2025. These tours offered an important opportunity for residents - whether or not they have children currently enrolled in the District - to explore key areas of the secondary school complex that are in need of renovation and repair.
May 19, 2025
RLPS Hosts Community Town Hall
RLPS Architects held a public Town Hall meeting on May 19, 2025, in the Elizabethtown Area Middle School auditorium. The meeting was open to the entire community.
- Presentation
- Town Hall Recording
- Community Survey (Open May 21 through June 5)
May 13, 2025
Board Receives Feasibility Study Update
During the regularly scheduled board meeting on May 13, 2025, the Elizabethtown Area School District Board of School Directors received an update from RLPS Architects on the status of the feasibility study.
March 25, 2025
Board Approves Addition of Student Count Survey
During the regularly scheduled board meeting on March 25, 2025, the Elizabethtown Area School District Board of School Directors approved a request from RLPS Architects to add a student count survey to their Feasibility Study at a cost of $5,000.
March 11, 2025
Board Discusses Request for Student Count Survey
During the regularly scheduled board meeting on March 11, 2025, the Elizabethtown Area School District Board of School Directors discussed a request from RLPS Architects to add a student count survey to their Feasibility Study at a cost of $5,000.
January 28, 2025
Board Approves Second Architectural Review of Secondary Complex
During the regularly scheduled board meeting on January 28, 2025, the Elizabethtown Area School District Board of School Directors approved RLPS Architects to conduct a second review of the High School/Middle School complex.
January 14, 2025
Board Considers Second Architectural Review of Secondary Complex
During the regularly scheduled board meeting on January 14, 2025, the Elizabethtown Area School District Board of School Directors discussed a second architect review of the High School/Middle School complex by a different architect.
December 3, 2024
Feasibility Study Presentation #3: Financing Overview
During the regularly scheduled board meeting on December 3, 2024, the Elizabethtown Area School District Board of School Directors viewed presentation #3 on the implications of the recently conducted feasibility study.
November 12, 2024
Feasibility Study Presentation #2: Financial Implications
During the regularly scheduled board meeting on November 12, 2024, the Elizabethtown Area School District Board of School Directors viewed presentation #2 on the implications of the recently conducted feasibility study.
October 8, 2024
Feasibility Study Presentation #1: Preliminary Financial Review
During the regularly scheduled board meeting on October 8, 2024, the Elizabethtown Area School District Board of School Directors viewed presentation #1 on the implications of the recently conducted feasibility study.
September 12, 2024
In Focus Article Provides Project Update
In Focus article published providing clarity on the current status of the EAMS/EAHS Building project.
September 10, 2024
Architectural Firm Presents Feasibility Study Findings
During the regularly scheduled board meeting on September 10, 2024, representatives from Crabtree, Rohrbaugh & Associates, the District’s architectural firm, presented their findings from a nearly year-long feasibility study.
September 26, 2023
Board Authorizes District-Wide Feasibility Study
During the regularly scheduled board meeting on September 26, 2023, the Board of School Directors authorized Crabtree, Rohrbaugh & Associates to complete a Feasibility study of all District facilities. This study will become part of the District's 5-year plan. There is no charge for this study.
September 12, 2023
Board Reviews Proposal for District-Wide Feasibility Study
During the regularly scheduled board meeting on September 12, 2023, the Board of School Directors discussed approval of Crabtree, Rohrbaugh & Associates Architects to complete a Feasibility study of all District facilities.