    July 9, 2018 (NEW)

    July 9, 2018 Photo Gallery Bainbridge Elementary project has reached substantial completion. Code inspections and design team inspections are underway to make certain the work done conforms with the approved design and expenditures. Project contractors are working on the end-of-project punch list to prepare the school to receive the furniture.  CLICK HERE for photo gallery.

     

     

    June 6, 2018                       

    June 6 photo gallery

    Bainbridge Elementary project nearing substantial completion. Interior painting, flooring, and mechanical work is ongoing, as well as finishing touches on exterior work. Landscaping and playground equipment installation underway. CLICK HERE for photo gallery.

     

     

    March 19, 2018

    March 19 2018 Gallery Exterior brick work nearing completion. Roofing work to begin in early April. Windows on new addition being installed. Drywall work ongoing on both new addition and existing building. Primer painting underway. Project is currently on schedule and no unforseen or identified issues encoutered to date that would adversely impact the completion date. CLICK HERE for photo gallery.

     

     

    January 29, 2018

    Photo Gallery Icon Both classroom additions are under roof and temporarily dried in. Exterior brick work continues on both classroom additions. Steel framing of the new cafeteria is almost complete. Drywall work in the interior is beginning on existing building while metal stud partitions are being complete in preparation of drywall work on new additions. Duct and piping work is ongoing. Project remains on schedule and no unforeseen or identified issues have been encountered to date.  CLICK HERE for photo gallery.

     

     

    December 15, 2017

    December 15 Photo Gallery - Image for slideshow Project is moving forward on schedule with classroom additions to be under roof by the end of the year. Interior block work is expected to be done over winter, which will then show the true feel of the space. Electrical, plumbing, and mechanical contractors are "chasing the Masons" to ensure all items that all rough-ins are concealed behind the wall. Interior color selections will be made before the Christmas break.  CLICK HERE for photo gallery.

     

     

    October 23, 2017

    October 23, 2017 Photo Gallery Work on footings and foundation is nearing completiton. Exterior wall work is underway.  Mechanical, electrical, and plumbing rough-ins has begun at existing building.  CLICK HERE for photo gallery.

     

     

     

     

    October 3, 2017

    October 3 Photo Gallery Work on footings and foundation is nearing completiton. Exterior wall work is underway.  Mechanical, electrical, and plumbing rough-ins has begun at existing building.  CLICK HERE for photo gallery.

     

     

     

     

    September 11, 2017

    September 11, 2017 photo gallery thumbnail Work on footings and foundation is 85% complete. In addition, the laying of underground piping and electrical raceways beneath floor slabs of new addition is underway. Mechanical, electrical, and plumbing rough-ins has begun at existing building. Work has begun on storm water management plan including underground drainage basin. CLICK HERE for photo gallery.

     

     

     

    August 25, 2017

    Photo Gallery - August 25, 2017 The new learning space begins to take shape as work on the Foundation for the addition continues. Demolition work continues as the site begins to gear up for the renovation. CLICK HERE for photo gallery.

     

     

     

     

    August 18, 2017

    Photo Gallery - August 18, 2017 Exterior and interior demolition continues while site preparation work for the new addition has started and the foundation has begun to take form for the learning space. CLICK HERE for photo gallery.

     

     

     

     

    August 10, 2017

    Photo Gallery August 10, 2017 Exterior and interior demolition continues at Bainbridge Elementary. In addition, extoerior site preparation work has progressed to include the foundation for the new addition being set. CLICK HERE for photo gallery.

     

     

     

    July 31, 2017

    Photo Gallery - July 31, 2017 Exterior and interior demolition is in full swing and the site is being prepared for renovation. Exterior demolition is to create the space for the new addition that will support a 21st century instruction model that includes critical thinking, collaboration, creativity, and communication. CLICK HERE for photo gallery.

     

     

    July 13, 2017

    July 13, 2017 Photo Gallery Image Exterior and interior demolition work continues at Bainbridge Elementary. Exterior demolition is to create the space for the new addition that will support a 21st century instruction model that includes critical thinking, collaboration, creativity, and communication. CLICK HERE for photo gallery.

     

     

    July 7, 2017

    July 7, 2017 Photo Gallery The Bainbridge Elementary School Renovation Project is underway. The first phase consists of demolition work to prepare the school for its new addition and interior overhaul. CLICK HERE for photo gallery.